Corridor improvements

Corridor improvement projects which are part of West Yorkshire-plus Transport Fund.

Projects within this area

Browse the different projects within this area by opening and closing the tabs below.

Corridor Improvement Programme

The Corridor Improvement Programme aims to deliver benefits for all road users with an emphasis on reducing journey times, in order to improve connectivity and accessibility to economic growth sites including those located in spatial priority areas. The aim is also to improve air quality and contribute towards tackling the climate emergency.

 

Phase 1

Bradford A6177 ORR Thornton Road

Project overview

This scheme focuses on traffic improvements at two junctions: the A6177 Whetley Lane/Toller Lane junction and the A6177 Thornton Road/Cemetery Road junction.

The improvements will be focused around the provision of two lane approaches where feasible, provision of dedicated turning facilities, and improvements for pedestrians and cyclists.

Once the scheme is delivered, it is anticipated that journey time reliability will improve on the western section of the A6177 Outer Ring Road and congestion will reduce along the A6177 Outer Ring Road.

The scheme's wider social benefits include a more attractive environment for the local community, and better quality of life, with reduced congestion improving air quality and connectivity to employment and housing.

 

Project Lead Bradford Council
District/ Area Bradford
Funding West Yorkshire plus Transport Fund- £10.2 million
Project Status Activity 4: Full Business Case
Start and end dates April 2020- May 2024
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch transport.projects@westyorks-ca.gov.uk

Last updated February 2024

Bradford Great Horton Road

Project overview

 

The proposed scheme will primarily provide a new link road between the Horton Park Avenue/Cecil Avenue junction and the All Saints Road/Dirkhill Road junction, as well as improvements to the Great Horton Road/Horton Grange Road junction.

The new link road will allow traffic movements to bypass the Great Horton Road/Horton Grange Road / All Saints Road junction.

It is also proposed that All Saints Road is changed to a one way southbound between Great Horton Road and Turner Place. This will reduce traffic conflicts, whilst increasing capacity.

The scheme's wider social benefits include a more attractive environment for the local community, and better quality of life, with reduced congestion improving air quality and connectivity to employment and housing.

 

Project Lead Bradford Council
District/ Area Bradford
Funding West Yorkshire plus Transport Fund - £6,257, 000 million
Project Status Activity 5: Delivery
Start and end dates February 2023 - February 2024 
Other funders None
Get in touch transport.projects@westyorks-ca.gov.uk

Last updated February 2024

Calderdale A58 A672

Project overview

A corridor improvement programme to improve journey time reliability on the A58/A672, particularly for public transport users. The scheme will aim to reduce congestion, attract new business so the area, occupy new employment, facilitate future housing growth, enhance active modes close gaps for active travel, minimise air pollution and to reduce collisions, particularly on collisions involving pedestrians and cyclists.

 

Project Lead Calderdale Council
District/ Area Calderdale
Funding West Yorkshire plus Transport Fund- £5,442,000 Million
Project Status Activity 5: Delivery
Start and end dates December 2021- October 2024
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch Thenextchapter@calderdale.gov.uk

Last updated February 2024

Calderdale A646/A6003 Corridor

Project overview

Halifax is identified as a spatial priority area in the SEP. Improved links to the economic opportunities available in Halifax from the Upper Calder Valley will connect people to higher value jobs, whilst improvements to air quality through reduced congestion will deliver a better environment, ensuring ‘good growth’ credentials of the SEP are met. Potential improvements to public realm will also improve quality of life.

As part of the WYKRN, the A646/A6033 provides a key role linking Calderdale to the Greater Manchester City Region and to Lancashire. Improvements to this route will ensure sustainable growth of Halifax and surrounding economic centres such as Copley, whilst boosting the visitor economy by enhancing links with neighbouring areas. Increased accessibility of Halifax from the west will also complement parallel improvements planned on the A646/A6033, helping erode the productivity gap that exists with other areas, reducing barriers that deter future investment and improving the quality of life for residents.

 

Project Lead Calderdale Council
District/ Area Calderdale
Funding

West Yorkshire plus Transport Fund- £4.687m million

Calderdale Council - £0.352 million

Project Status Activity 5: Delivery
Start and end dates December 2021 - December 2024
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch Thenextchapter@calderdale.gov.uk

Last updated February 2024

Kirklees A62 Smart Corridor

Project overview

To increase capacity on the A62 to a level which can accommodate the predicted demand from the level of residential and employment growth around the corridor. Easing congestion issues which are a lead cause of air quality issues, slow peak journey times and an inefficient highway network but building in a more sustainable transport network and modal shift from the private car.

The scheme seeks to improve access to existing and proposed employment sites, the Cooper Bridge Enterprise Zone and the strategic and primary route network along with improve the safety of the A62 road corridor, alongside improving the detrimental environmental issues.

Enhancing the accessibility of potential housing growth allocations in the Local Plan, supporting housing and employment allocations through a sustainable transport network.

 

Project Lead Kirklees Council
District/ Area Kirklees
Funding West Yorkshire plus Transport Fund- £8.35 million
Project Status Activity 6 - Closure and Review
Start and end dates December 2021 - June 2023
Delivery partners West Yorkshire Combined Authority and Kirklees Council
Other funders None
Get in touch major.transport@kirklees.gov.uk

Last updated February 2024

Kirklees Holmfirth Town Centre Access Plan

Project overview

The new link will allow for the dilution of traffic over a wider area thus reducing traffic congestion in and around Victoria Street, A6204 and Towngate for the benefit of all travel modes and allow for a much improved pedestrian environment not only on Victoria Street but within the wider area.

 

Project Lead Kirklees Council
District/ Area Kirklees
Funding West Yorkshire + Transport Fund - £5.17 million
Project Status Activity 4: Full Business Case
Start and end dates 2017- September 2024
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch Major.transport@kirklees.gov.uk

Last updated February 2024

Kirklees Huddersfield Southern Corridor

Project overview

This scheme aims to deliver public realm improvements to the Queensgate / Shorehead section of Huddersfield Ring Road, making it a more attractive environment for pedestrians and cyclists whilst also delivering journey time benefits to motorised traffic.

Additional highway improvement schemes are also being considered for the congestion hotspots of Longroyd Bridge, Folly Hall and Lockwood Bar, Huddersfield.

 

Project Lead Kirklees Council
District/ Area Kirklees
Funding West Yorkshire + Transport Fund- £10.42 million
Project Status Activity 5: Delivery
Start and end dates Spring 2020- April 2025
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch Major.transport@kirklees.gov.uk

Last updated February 2024

Leeds Dawson's Corner

Project overview

Dawson’s Corner is a key junction between Leeds (10km west) and Bradford (5km east) located on the Ring Road in Pudsey.

There are currently no crossing facilities on Bradford Road. There are pedestrian and cycle crossings on all other arms.

The proposals are to provide a fully remodelled and enlarged signalised junction, utilising third party land to the southwest of the existing junction.

It is anticipated the scheme will reduce congestion, leading to smoother flows and improved air quality. Enhanced landscaping. Cycle / pedestrian provision and bus route improvements will promote alternative mode of transport.

 

Project Lead Leeds City Council
District/ Area Leeds
Funding

West Yorkshire + Transport Fund - £15 million

LPTIP: £4 million

Project Status Activity 4: Full Business Case
Start and end dates Construction estimated to commence Summer 2024 for completion in Winter 2025
Delivery partners West Yorkshire Combined Authority
Other funders

LPTIP- £4 million

Other private sector funding- £1.05 million

Get in touch Connectingleeds@leeds.gov.uk

Last updated February 2024

Leeds Fink Hill

Project overview

Fink Hill is located on the A6120 Outer Ring Road and forms a four arm signal controlled junction.

Pedestrian facilities at this junction are currently poor with only one pelican crossing on the A6120 (E), holding traffic across all three lanes. There are no formal crossings on Fink Hill, Parkside or A6120 (W). The junction currently experiences congestion which delays movement along the A6120.

The objectives of this scheme are to improve the local area for pedestrian and cycle safety, reduce severance between communities and jobs, increase journey time reliability and reduce traffic congestion and delays.

 

Project Lead Leeds City Council
District/ Area Leeds
Funding

West Yorkshire + Transport Fund - £3.257 million

Levelling Up Fund - £4.696 million

Project Status Activity 6 - Closure and Review
Start and end dates April 2022- January 2024
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch connectingleeds@leeds.gov.uk

Last updated February 2024

Leeds Dyneley Arms

Project overview

Dyneley Arms is a key junction on the A660 and A658 between Leeds (12km SE), Bradford (13km SW) and Harrogate (12km NE).

The junction, due to its remote location, currently has no specific pedestrian or cycle facilities.

The proposal is for a ‘quick-win’ scheme involving technology and detection improvements, plus widening the centre of the junction to prevent right-turning vehicles from obstructing ahead movements.

It is anticipated that improved layout will lead to smoother flows and positive impact on air quality. Bus service journey times reliability, advanced stop lines for cyclist and potential new pedestrian crossing will promote alternative mode of transport.

 

Project Lead Leeds City Council
District/ Area Leeds
Funding West Yorkshire + Transport Fund - £2.336 million
Project Status Activity 6 - Closure and Review
Start and end dates 2021 - August 2023
Delivery partners West Yorkshire Combined Authority
Other funders None
Get in touch connectingleeds@leeds.gov.uk

Last updated February 2024

Wakefield A650 Newton Bar

Project overview

The A650 experiences high congestion levels, particularly around Newton Bar and the existing roundabout.

The roundabout connects the A650 dual carriageway to Junction 41 of the M1; the A61 Leeds Road 110 bus routes to the city centre; and Bar Lane to Pinderfields Hospital and the City Fields housing development.

This scheme aims to improve the highway capacity of the roundabout in order to manage the traffic flows and facilitate the development of future housing. The roundabout will be increased in size and traffic signals installed to better control the flow of traffic along the corridor.

This scheme also improves pedestrian and cycle facilities across the roundabout to improve health and safety aspects. 

 

Project Lead Wakefield Council
District/ Area Wakefield
Funding West Yorkshire plus Transport Fund – Corridor Improvement Programme- £9.135 million
Project Status Activity 6 - Closure and Review
Start and end dates Construction start December 2021 – Construction complete January 2023
Delivery partners West Yorkshire Combined Authority
Other funders S106 funding- To be confirmed  
Get in touch Transplan@wakefield.gov.uk

Last updated February 2024

Phase 2

Phase 2 of the CIP is to undertake feasibility work to consider wider corridor interventions and strategy development in order to identify further measures to build on the benefits achieved through Phase 1.

8 schemes are now being taken forward under Phase 2 of the programme.

A61 North, Leeds - Scott Hall Road

Project overview

The scheme will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Leeds City Council
District/ Area West Yorkshire 
Funding  West Yorkshire plus Transport Fund- £0.88 million. This is a pipeline scheme 
Project Status

Activity 3 - Outline Business Case. This is a pipeline scheme to get Full Business Case

Start and end dates Scheme has been paused
Delivery partners

Leeds Council, West Yorkshire Combined Authority 

Other funders To be confirmed
Get in touch TransportProjects@westyorks-ca.gov.uk
Bradford A6177 - Cutler Heights

Project overview

Currently paused

Delivery of the A6177 and Cutler Heights/Dick Lane corridor scheme is a key element of the strategy to provide the Bradford area with the infrastructure it needs to support growth.

The scheme will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Bradford Council
District/ Area West Yorkshire 
Funding  West Yorkshire plus Transport Fund - £10.01 million.  
Project Status

Activity 3 - Outline Business Case

Start and end dates This scheme is currently paused
Delivery partners

Bradford Council

Other funders To be confirmed
Get in touch/ contact information  TransportProjects@westyorks-ca.gov.uk

Last updated February 2024

Calderdale - A629N Scheme

Project overview

The scheme will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Calderdale Council
District/ Area West Yorkshire 
Business Case Summary

View document

Funding  West Yorkshire plus Transport Fund - £6.1 million  
Project Status

Funded by CIP to Activity 3 - Outline Business Case

This scheme will continue to be funded by Levelling Up Fund (LUF)

Start and end dates 2020-2025
Delivery partners

Calderdale Council, West Yorkshire Combined Authority 

Other funders To be confirmed
Get in touch/ contact information  TransportProjects@westyorks-ca.gov.uk

Last updated in February 2024

Kirklees - A629 Scheme

Project overview

The scheme will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Kirklees Council 
District/ Area West Yorkshire 
Funding  West Yorkshire plus Transport Fund- £0.6 million 
Project Status

Activity 3: Outline Business Case

Start and end dates 2020- April 2024
Delivery partners

Kirklees Council, West Yorkshire Combined Authority 

Other funders N/A
Get in touch/ contact information  TransportProjects@westyorks-ca.gov.uk

Last updated January 2024

Leeds - A58 Roundhay Road

Project overview

The scheme will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Leeds City Council
District/ Area West Yorkshire 
Funding  West Yorkshire plus Transport Fund- £9.530 million 
Project Status

Activity 4 - Full Business Case

Start and end dates 2020 - TBC
Delivery partners

Leeds City Council, West Yorkshire Combined Authority 

Other funders N/A
Get in touch/ contact information 

TransportProjects@westyorks-ca.gov.uk

Last updated September 2023

Leeds - A660 Lawnswood Roundabout

Project overview

The A660 is one of the most congested corridors in Leeds. It experiences high traffic flows as well as seeing some of the highest volumes of pedestrians and cyclists, often competing for road space with HGVs and more than 60 buses per hour at peak times.


Initially included under the Leeds Public Transport Investment Programme (LPTIP), the proposed A660 Lawnswood Roundabout scheme formed part of the Corridor Improvement Programme (CIP) to Outline Business Case stage, and is now being funded by City Regional Sustainable Transport Settlement (CRSTS) for Full Business Case to delivery.

This scheme will deliver improvements to the Lawnswood Roundabout section of the A660 corridor in Leeds including a new 435 metre section of outbound (northbound) bus lane, the upgrade of advisory cycle lanes to dedicated facilities, for approximately 350 metres, in both directions and a controlled pedestrian crossing.

 

Project Lead Leeds City Council
District/ Area West Yorkshire 
Funding 

West Yorkshire plus Transport Fund- £0.83 million.

City Regional Sustainable Transport Settlement Fund (CRSTS) - £TBC

Project Status

Funded by CIP to Activity 3: Outline Business Case and now funded by CRSTS for Activity 4 and delivery.

Start and end dates 2018- 2024
Delivery partners

Leeds Council, West Yorkshire Combined Authority 

Other funders N/A
Get in touch/ contact information  connectingleeds@leeds.gov.uk

Last updated February 2024

Wakefield A638 Doncaster Road

Project overview

Currently paused

Delivery of the A638 Doncaster Road Corridor scheme is a key element of the strategy to provide the Wakefield area with the infrastructure it needs to support growth.

This scheme will enable the local road network to operate more efficiently by encouraging modal shift towards sustainable modes, through providing infrastructure to support walking, cycling and bus usage promoting associated health benefits, and provide capacity for growth.

 

Project Lead Wakefield Council
District/ Area West Yorkshire 
Funding  West Yorkshire plus Transport Fund- £6.30 million 
Project Status

Activity 4: Full Business Case

Start and end dates This scheme is currently paused.
Delivery partners

West Yorkshire Combined Authority 

Other funders N/A
Contact TransportProjects@westyorks-ca.gov.uk

Last updated February 2024

Wakefield A639 Park Road (development)

Project overview

Delivery of the A639 Park Road corridor scheme is a key element of the strategy to provide the Pontefract and Castleford area with the infrastructure it needs to support growth. It will enable the local road network to operate more efficiently by reducing congestion, improving journey times, providing infrastructure to support modal shift towards more sustainable modes allowing associated health benefits, and provide capacity for growth.

 

Project Lead Wakefield Council
District/ Area West Yorkshire 
Funding 

West Yorkshire plus Transport Fund- £.57 million. 

Levelling Up Fund (LUF) - £TBC

Project Status

Funded by CIP to Activity 3 - Outline Business Case. To be funded by LUF from Activity 4 - Full Business Case.

Start and end dates 2020- 2026
Delivery partners

West Yorkshire Combined Authority 

Other funders N/A
Contact TransportProjects@westyorks-ca.gov.uk

Last updated February 2024

Other corridor improvement projects

A641 Bradford Huddersfield Corridor

Project overview

The A641 forms part of the Key Route Network between Huddersfield and Bradford and provides an essential link from Brighouse to surrounding centres and the M62 J25 (via the A644). The scheme comprises of a series of interventions proposed for delivery in Brighouse town centre and along the A641 corridor The scheme is to be funded from the West Yorkshire plus Transport Fund. 

Carrying more than 20,000 vehicles a day, the route has significant traffic congestion issues in a number of locations.

Reducing journey times along the route will increase economic investment in the area by unlocking land for employment and housing growth, as well as improving conditions for all users. This will include increasing the use of sustainable transport and improving facilities for public transport.

The project will be delivered in cooperation with the investment projects managed by both Kirklees Council and Bradford Council.

 

Project Lead Calderdale Council
District/ Area Calderdale
Funding

West Yorkshire plus Transport Fund- £75.5 million

Other capital funding is planned to be provided by CMBC through planning obligations (TBC Winter 2024).

Project Status Activity 4: Full Business Case
Start and end dates 2017- 2026
Delivery partners Calderdale and West Yorkshire Combined Authority
Other funders TBC
Get in touch (contact information)

thenextchapter@calderdale.gov.uk

https://calderdalenextchapter.co.uk/projects/a641-improvement-scheme 

Last updated in September 2023

A653 Leeds to Dewsbury Corridor

Project overview

This scheme for the A653 corridor from Dewsbury into Leeds will see capacity enhancement measures to reduce congestion at 'hot spot' junctions along with public transport improvement such as the introduction of a limited stop bus service between Dewsbury and Leeds.

Reduced and more reliable journey times will help support job retention and growth along the corridor as well as improved local air quality though reduced CO2 emissions.

 

Project Lead Kirklees Council
District/ Area Kirklees
Funding

Total scheme cost- £7.825 million

West Yorkshire Plus Transport Fund- £7.175 million

Project Status Activity 4 - FBC
Start and end dates TBC
Delivery partners Kirklees and Leeds City Council
Other funders S106 contributions 
Get in touch major.transport@kirklees.gov.uk

Last updated February 2024

Bradford to Shipley Corridor

Project overview

This scheme aims to improve the links between Bradford city centre and Shipley. Proposals include multi-modal enhancements along Manningham Lane/Bradford Road which are focused on boosting journey time reliability, connectivity and improving bus and cycle journeys.

The Bradford-Shipley Route Improvement Scheme (BSRIS) will primarily deliver improvements at key junctions in Bradford to enhance the highway capacity and connectivity to/from Shipley town centre. The scheme will also improve accessibility to Frizinghall rail station, improve the urban environment at Bradford Beck, and improve the public transport, walking and cycling provision along the Manningham Lane corridor. Combined, these improvements will help to reduce carbon emissions, alleviate flood risk and create better places along the corridor.

The BSRIS is anticipated to reduce traffic congestion, improve journey time reliability for all modes, improve air quality and increase road safety. A key local benefit of the scheme will be improvements to green spaces along the route, providing pockets of wildlife and pleasant walking paths which can be used by residents. The scheme supports delivery of inclusive growth by facilitating new housing and employment opportunities and a better quality of life, with better air quality, encouraging active mode travel (walking, cycling), improving rail accessibility, and enhancing the urban environment, specifically at Bradford Beck.

The scheme is anticipated to reduce current and forecast congestion, improve journey time reliability for all modes, and widen the sustainable travel opportunities with enhanced cycling and walking infrastructure and connectivity to rail.

 

Project Lead Bradford Council
District/ Area Bradford
Funding West Yorkshire Plus Transport Fund - £11.5 million
Project Status Activity 3 - OBC
Start and end dates Scheme is being pipelined at the Full Business Case stage following the November 2022 inflation review
Delivery partners Bradford City Council
Other funders None
Get in touch Email the West Yorkshire Combined Authority

Last updated in September 2023

Castleford Growth Corridor Scheme

Project overview

The Aire River Growth Corridor is within Castleford and has been designated as a 'Housing Zone'. Improvements to the transport infrastructure are needed to accommodate additional new homes planned for the area, and employment growth expected in the town.

This scheme aims to construct a new link road, improving the highway and reducing congestion. Flood mitigation measures will also be installed and pedestrian crossing facilities will be improved. A cycle lane will also be added to improve accessibility for cycle users along Aire Street and Wheldon Road.

The Castleford Growth Corridor Scheme will provide this by reducing congestion and improving accessibility.

This scheme will also provide a new public realm along the waterfront.

 

Project Lead Wakefield Council
District/ Area Wakefield
Funding West Yorkshire-plus Transport Fund - £9.27m
Project Status Activity 4: Full Business Case 
Start and end dates April 2024 - January 2025
Delivery partners West Yorkshire Combined Authority
Other funders Wakefield Council - £221k
Get in touch Transplan@wakefield.gov.uk

Last updated in February 2024