The Kirkgate Highways scheme is the first phase of the highway improvements identified for the “Wakefield City Centre Package” within the approved West Yorkshire Transport Fund scheme programme.

This scheme aims to improve connectivity within the Kirkgate area and to the rail station, attract new development to support economic growth and improve health and safety within the area.

The Chantry Road roundabout is to be improved and traffic signals are to be installed to help pedestrians and cyclists to cross safely.

By putting new infrastructure in place it is hoped this will support future development and investment in this part of the city.

Project Lead

 

Wakefield Council

District/ Area

Wakefield

 

Business case summary

 

 

Funding

West Yorkshire plus Transport Fund- £5.5 million

 

Project Status

Activity 6: Delivery

 

Start and end dates

Construction start May 2017 – Completion on site due August 2018.

 

Delivery partners

 

 

Other funders

 

 