Corridor Improvement Programme Phase 1 Wakefield A650

 

 

CIP Phase 1 Wakefield A650 map

The A650 experiences high congestion levels, particularly around Newton Bar and the existing roundabout.  

The roundabout connects the A650 dual carriageway to Junction 41 of the M1; the A61 Leeds Road 110 bus routes to the city centre; and Bar Lane to Pinderfields Hospital and the City Fields housing development.

This scheme aims to improve the highway capacity of the roundabout in order to manage the traffic flows and facilitate the development of future housing. The roundabout will be increased in size and traffic signals installed to better control the flow of traffic along the corridor.

This scheme also improves pedestrian and cycle facilities across the roundabout to improve health and safety aspects. 

Project Lead

 

Wakefield Council

District/ Area

Wakefield

 

Business case summary

 

 

Funding

West Yorkshire plus Transport Fund – Corridor Improvement Programme- £4.5 million

 

Project Status

Activity 3: Outline Business Case

 

Start and end dates

Construction start January 2020 – Construction complete December 2020.

 

Delivery partners

West Yorkshire Combined Authority

 

Other funders

S106 funding- To be confirmed  

 

Get in touch (contact information)